Paving work on Blackcomb Way between Sundial and Village Gate Boulevard: May 4 to 8
Construction to improve the paving on Blackcomb Way is happening Monday, May 4 to Friday, May 8 from 7 a.m. to 8 p.m.
Blackcomb Way will have single-lane alternating traffic, minor traffic delays and potential congestion (see map below). Expect construction vehicles and increased noise. Please follow signage and traffic controllers around the work zone.
Paving work on Glacier Lane near Glacier Ridge Employee Housing: May 11 to 15
Construction to improve the paving on Glacier Lane near the Glacier Ridge Employee Housing from the Blackcomb Gate to Glacier Drive (see map below) is happening Monday, May 11 to Friday, May 15 from 7 a.m. to 8 p.m.
Overview
The goal of this project is to rehabilitate and improve the pavement of various roads throughout the Resort Municipality of Whistler. Below is a list of 17 segments of the road that will be rehabilitated.
Whistler Village
- Segment 1.0: Blackcomb Way – Sundial Place to Village Gate Blvd
- Segment 2.0: Glacier Lane – Blackcomb Gate to Glacier Drive
Alpine Meadows
- Segment 3.0: Alpine Way – McKeevers Pl to Hwy #99
- Segments 4.0 & 5.0: Drifter Way – Matterhorn Drive to Valley DriveSegments
- Segments 4.0 & 5.0: Drifter Way – Matterhorn Drive to Valley Drive
- Segments 6.0 & 7.0: Mountainview Drive – Valley Drive to Parkwood Drive
- Segment 8: Matterhorn Drive – Forest Ridge Drive to Rainbow Drive North (SB)
Nordic Estates
- Segment 9.0: Eva Lake Road – Whistler Road to Garibaldi Way (SB)
Emerald Estates
- Segments 10.0 & 11.0: Emerald Drive – Emerald Drive to Hwy 99 (EB AND WB)
Whistler Cay
- Segment 12.0: Lorimer Road – Piccolo Road to St Andrews Way (SB)
- Segment 13.0: Lorimer Road – St Andrews Way to Hwy 99 (NB)
- Segment 14.0: Lorimer Road – Crabapple Drive to Balsam Way
Blueberry
- Segment 15.0: Blueberry Drive – Heron Place to Beaver Lane (SB)
- Segment 16.0: Blueberry Drive – St Moritz Cr to Ptarmigan Place
Function Junction
- Segment 17.0: Alpha Lake Road – Miller Creek Road Crosswalk to 1208 Alpha Lake Road
Construction impacts
Vehicles may experience minor delays and congestion during construction. Notice will be provided to affected residents, businesses, schools, and services.
Construction activities will generate equipment noise an increase the number of construction vehicles in the work area. Minor delays and single-lane alternating traffic may occur throughout the project.
Traffic control personnel will ensure safety and smooth traffic flow. We kindly ask everyone to follow their instructions and adhere to all construction signs.
Timeline
Construction period: May 2026 – July 2026