South Whistler Water Supply Upgrade – Phase 2

Overview

The South Whistler Water Supply Upgrade project will ensure a reliable and resilient water supply for residents and businesses in the Function Junction, Cheakamus Crossing, Creekside, and surrounding areas.

What’s happening

Phase 1 completed 2023: New water main sections installed to connect the existing water systems in Function Junction and Cheakamus Crossing. This created a backup system in case of disruptions in either area.

Phase 2: A new water pump and treatment station will be built beside the existing Cheakamus Crossing well and pump station. This station will:

  • Adjust water acidity (pH): Ensure the water meets optimal quality standards.
  • Boost water pressure: Allow for efficient water distribution during peak demand periods.
  • Increase water flow flexibility: Enable water movement from south Whistler (during high supply) to support areas like Creekside, and vice versa.

Benefits

  • Enhanced water security: The interconnected system provides a reliable water source even if there are issues in one specific area.
  • Improved water quality: The treatment station ensures consistent water quality that meets all regulations.
  • Efficient water distribution: The upgraded system allows for optimized water flow throughout Whistler.

Locations

  • Lynham Road (W212) Pump Station, north of the Function Junction depot
  • Valley trail at the intersection of Lynham Road
  • Whistler Interpretive Forest parking lot
  • Water Pump Station and 1101 Cheakamus Lk. Rd.

Construction impact

Expect equipment noise and increased numbers of construction vehicles. Pedestrians and cyclists will be detoured around the work site. This will be clearly marked with traffic cones, and traffic control persons when required. 

Timeline

  • 2022: Design (complete)
  • Winter 2023: Procurement and Council approval (complete)
  • Spring to fall  2023: Phase 1 civil works (complete)
  • Spring 2024 to summer 2025: Phase 2 Construction of new treatment, pump station and civil work tie ins.